The Smithe construction update

Despite the restrictions of COVID-19, construction at The Smithe has continued safely and successfully with a reduced site capacity and essential measures in place.

The exterior is progressing with metal panel installation, soffit painting, and residential and office glass installation. In-suite steel stud framing is done up to level 22 and drywall is up to level 10, while interior door installation and prime painting is underway. Tile, cabinetry, and appliance delivery will be commencing in the coming weeks. The tower crane is scheduled to be removed later this month.

Here are some recent photos.

the smithe construction

the smithe office podium

UrbanYVR recently posted an article with more great photos – check it out here.

Be sure to follow us on Instagram, Facebook and Twitter for frequent cosntruction updates and photos.

 

 

 

 